- What is the primary responsibility of a Scrum Master in SAFe?
- To coach the team on Agile practices, remove impediments, and facilitate Scrum events.
- Who owns the product backlog and defines priorities for what the team builds?
- The Product Owner.
- What does a Release Train Engineer (RTE) do?
- Coaches and guides the Agile Release Train, facilitates PI Planning, and helps manage ART risks and dependencies.
- Define the Agile Coach role in SAFe.
- An experienced practitioner who mentors teams and organizations in Agile practices, SAFe principles, and mindset shifts.
- What is a Business Owner's responsibility in SAFe?
- To represent stakeholder and customer interests, define and communicate the business vision, and help prioritize value delivery.
- Who manages investment strategy and allocates funding across programs?
- The Lean Portfolio Manager.
- What is a Solution Manager responsible for?
- Defining and communicating the solution vision, coordinating multiple ARTs, and managing solution roadmaps.
- Describe the System Architect role.
- Defines system architecture and technical vision, ensures consistency across teams, and manages architectural decisions.
- What is Program Increment (PI) Planning?
- A two-day event where the ART plans the work for the upcoming PI (8-10 weeks), aligns on dependencies, and commits to goals.
- What occurs during a System Demo in SAFe?
- Integrated teams showcase completed work at the end of each iteration to stakeholders and gather feedback.
- What is Inspect and Adapt (I&A)?
- A structured event at the end of each PI where the ART reviews results, identifies improvement opportunities, and plans next steps.
- Describe the Daily Standup in SAFe.
- A 15-minute daily meeting where team members share progress, discuss blockers, and coordinate work.
- What is the goal of Sprint Planning?
- For the team to define the sprint goal, select backlog items to complete, and estimate the work.
- What happens during Sprint Review?
- The team demonstrates completed work, gathers feedback from stakeholders, and updates the product backlog.
- What is Backlog Refinement in SAFe?
- An ongoing activity where the Product Owner and team clarify requirements, break down stories, and estimate items before sprints.