WBS, critical path method, float, estimation techniques, budgeting and baseline control.
41 cards · basic cards · AI-written, checked twice. Edit anything.
- What is a Work Breakdown Structure (WBS)?
Show answer
A hierarchical decomposition of the project scope into smaller, manageable work components, organized by phase or deliverable.
- What is the primary purpose of creating a WBS?
Show answer
To organize and define the total scope of work, clarify deliverables, and establish a framework for planning and control.
- What is the lowest level in a WBS called?
Show answer
Work package, the level at which work is planned, estimated, and controlled.
- Define the Critical Path in project management.
Show answer
The longest sequence of dependent activities that determines the minimum project duration.
- How is the Critical Path identified?
Show answer
By performing forward and backward pass calculations through the network diagram to find the path with the longest total duration.
- What is the forward pass in Critical Path Method?
Show answer
A calculation that determines the earliest start and earliest finish dates for each activity by moving forward through the network.
- What is the backward pass in Critical Path Method?
Show answer
A calculation that determines the latest start and latest finish dates for each activity by moving backward through the network.
- What is Total Float?
Show answer
The amount of time an activity can be delayed without delaying the project completion date, calculated as LS minus ES (or LF minus EF).
- What is Free Float?
Show answer
The amount of time an activity can be delayed without delaying the early start of any successor activity.
- Which activities have zero float?
Show answer
Activities on the critical path, as any delay in these activities will delay project completion.
- What is the Three-Point Estimation technique?
Show answer
An estimation method using optimistic, pessimistic, and most likely values to calculate expected duration or cost.
- What is the PERT formula for expected duration?
Show answer
Expected duration equals (Optimistic plus 4 times Most Likely plus Pessimistic) divided by 6.
- What is Parametric Estimation?
Show answer
A statistical technique that uses project parameters and historical data to estimate costs or durations for activities.
- What is Analogous Estimation?
Show answer
A technique that uses historical data from similar projects to estimate costs or durations for current project activities.
- What is Bottom-Up Estimation?
Show answer
An estimation approach where detailed estimates are developed for individual work packages and then aggregated to higher levels.