FlashKeepers

Project Management · PMP · Professional Certifications

PMP: Earned Value Management Formulas

Earned value management formulas (CPI, SPI, EAC, CV, SV) as cloze cards with each variable defined.

About this set

35 cloze cards for PMP Project Management. It opens with "Cost Variance (CV) is calculated as ____" and "Schedule Variance (SV) is calculated as ____". More Professional Certifications decks are listed below.

35 cards · cloze cards · AI-written, checked twice. Edit anything.

Study this set free Look inside first Get FlashKeepers for iPhone

Opens in your browser, no account. Get the iPhone and iPad app · Android app

Cost Variance (CV) is calculated as ____
Show answerEV - AC
Schedule Variance (SV) is calculated as ____
Show answerEV - PV
Cost Performance Index (CPI) is calculated as ____
Show answerEV / AC
Schedule Performance Index (SPI) is calculated as ____
Show answerEV / PV
Variance at Completion (VAC) is calculated as ____
Show answerBAC - EAC
Estimate at Completion when costs have been atypical is ____
Show answerAC + (BAC - EV)
Estimate at Completion when current cost efficiency continues is ____
Show answerAC + ((BAC - EV) / CPI)
Estimate at Completion using simplified CPI projection is ____
Show answerBAC / CPI
Estimate to Complete (ETC) is calculated as ____
Show answerEAC - AC
To Complete Performance Index (TCPI) based on BAC is ____
Show answer(BAC - EV) / (BAC - AC)
To Complete Performance Index (TCPI) based on EAC is ____
Show answer(EAC - EV) / (EAC - AC)
What does AC stand for in earned value management?
Show answerActual Cost
What does EV stand for in earned value management?
Show answerEarned Value
What does PV stand for in earned value management?
Show answerPlanned Value
What does BAC stand for in earned value management?
Show answerBudget at Completion

20 more cards in the app

Study this set free