Earned value management formulas (CPI, SPI, EAC, CV, SV) as cloze cards with each variable defined.
35 cards · cloze cards · AI-written, checked twice. Edit anything.
- Cost Variance (CV) is calculated as ____
Show answer
EV - AC
- Schedule Variance (SV) is calculated as ____
Show answer
EV - PV
- Cost Performance Index (CPI) is calculated as ____
Show answer
EV / AC
- Schedule Performance Index (SPI) is calculated as ____
Show answer
EV / PV
- Variance at Completion (VAC) is calculated as ____
Show answer
BAC - EAC
- Estimate at Completion when costs have been atypical is ____
Show answer
AC + (BAC - EV)
- Estimate at Completion when current cost efficiency continues is ____
Show answer
AC + ((BAC - EV) / CPI)
- Estimate at Completion using simplified CPI projection is ____
Show answer
BAC / CPI
- Estimate to Complete (ETC) is calculated as ____
Show answer
EAC - AC
- To Complete Performance Index (TCPI) based on BAC is ____
Show answer
(BAC - EV) / (BAC - AC)
- To Complete Performance Index (TCPI) based on EAC is ____
Show answer
(EAC - EV) / (EAC - AC)
- What does AC stand for in earned value management?
Show answer
Actual Cost
- What does EV stand for in earned value management?
Show answer
Earned Value
- What does PV stand for in earned value management?
Show answer
Planned Value
- What does BAC stand for in earned value management?
Show answer
Budget at Completion