- Which PRINCE2 principle requires a project to remain justified?
Show answer
Continued Business Justification
- Which PRINCE2 principle emphasizes extracting value from past experiences?
Show answer
Learn from Experience
- Which PRINCE2 principle establishes clear accountability in a project?
Show answer
Defined Roles and Responsibilities
- Which PRINCE2 principle divides a project into phases?
Show answer
Manage by Stages
- Which PRINCE2 principle lets a manager act only within defined limits?
Show answer
Manage by Exception
- Which PRINCE2 principle shifts focus from activities to outcomes?
Show answer
Focus on Products
- Which PRINCE2 principle means fitting the method to the project?
Show answer
Tailor to Context
- What process prepares the groundwork before project initiation?
Show answer
Starting Up a Project
- What process formally authorizes and sets up the project?
Show answer
Initiating a Project
- What process is owned by the Project Board to steer the project?
Show answer
Directing a Project
- What process monitors daily work delivery within a stage?
Show answer
Controlling a Stage
- What process is where the team delivers the actual products?
Show answer
Managing Product Delivery
- What process occurs between stages to review progress?
Show answer
Managing a Stage Boundary
- What process formally concludes the project?
Show answer
Closing a Project
- What theme defines why the project is happening?
Show answer
Business Case