FE Civil: Construction and Project Management

Critical path method, earned value, scheduling, cost estimating, safety, and construction materials such as concrete mixes.

About this set

35 basic cards for FE Civil Civil Engineering. Set 1 of 5 in FE Civil. It opens with "What is the critical path in a project network?" and "What does slack or float mean in CPM analysis?". More Professional Certifications decks are listed below.

35 cards · basic cards · AI-written, checked twice. Edit anything.

Study this set free Look inside first Get FlashKeepers for iPhone

Opens in your browser, no account. Get the iPhone and iPad app · Android app

What is the critical path in a project network?
Show answerThe longest sequence of dependent activities that determines the minimum project duration.
What does slack or float mean in CPM analysis?
Show answerThe amount of time an activity can be delayed without delaying the project completion date.
What determines the minimum project duration in a CPM network?
Show answerThe length of the critical path.
What is the difference between total float and free float?
Show answerTotal float is the delay allowed without delaying project completion; free float is the delay allowed without delaying the next activity.
What is a dummy activity in a CPM network diagram?
Show answerA zero-duration activity used to show logical dependencies without consuming time or resources.
What does a forward pass calculate in CPM?
Show answerThe earliest start and earliest finish times for each activity.
What does Earned Value (EV) represent?
Show answerThe value of work actually completed, based on the approved project budget for that work.
What is the Cost Performance Index (CPI)?
Show answerThe ratio of Earned Value to Actual Cost: CPI = EV / AC. A CPI greater than 1 means the project is under budget.
What is the Schedule Performance Index (SPI)?
Show answerThe ratio of Earned Value to Planned Value: SPI = EV / PV. An SPI greater than 1 means the project is ahead of schedule.
What is the Estimate at Completion (EAC)?
Show answerThe projected total cost of the project at completion, calculated as BAC / CPI.
What does BCWP stand for?
Show answerBudgeted Cost of Work Performed. It is the same as Earned Value (EV).
What does BCWS stand for?
Show answerBudgeted Cost of Work Scheduled. It is the same as Planned Value (PV).
What does ACWP stand for?
Show answerActual Cost of Work Performed. It is the same as Actual Cost (AC).
What is the Variance at Completion (VAC)?
Show answerThe difference between Budget at Completion and Estimate at Completion: VAC = BAC - EAC. A positive VAC means the project is under budget.
What is a Gantt chart?
Show answerA horizontal bar chart that shows project tasks, their durations, and their relationships over time.